Detailed Construction Scope of Work Template

Attachment #3 QQ-01765
Detailed Scope of Work
Page 2 of 13
1. Site permit and zoning, by owner; fees are waived by Loudoun County Department of Building
and Development.
2. Code modification/waiver for the second bathroom requirement by IPC, by owner.
3. Building Permit/s, including the demolition of the building, and foundation wall are the General
contractor’s responsibility; fees are waived by Loudoun County Department of Building and
Development.
4. Building permit to re-build the pre-engineered building, the foundation, and the wing walls are
the responsibility of the GC; Fees are waived by the Loudoun County Department of Building
and Development.
5. Electrical permit and plans (if required by Building Development), is the contractor’s
responsibility, fees are waived by the Loudoun County Department of Building and
Development.
6. Mechanical permit and plans (if required by Building Development), contractor’s responsibility,
fees are waived by the Loudoun County Department of Building and Development.
7. Plumbing permit and plan (if required by Building Development), contractor’s responsibility,
fees are waived by the Loudoun County Department of Building and Development.
8. Health department approval, well and septic connections, contractor’s responsibility, fees are
waived. Contractor is required to check with the department to obtain information on the
required plans and permits, if any.
Submittals:
1. Submit a construction schedule and the sequence of work to the owner; please note the county
holiday schedule when preparing the construction schedule. Once approved, any change to
the schedule shall be approved in advance by the owner.
2. Provide the list of professionals and the subcontractor’s, once selected, to the owner.
3. Submit the Architectural plans as part of the plan submittal; Prepared by the owner.
4. Complete sets of instructions for field procedures for erection and adjustment prior to
construction to the owner.
5. The manufacturer shall supply the contractor with Pre-engineered shop drawings; the said
drawings shall show the dimensions, complete erection drawings with the proper identification
and assemblage of the building component, all relevant details, along with the calculations
booklet sealed and signed by an engineer registered in the Common Wealth of VA. Owner’s
approval is required prior to any submittal to the county or the design engineer. A copy of the
said material shall be provided to the owner.
6. The manufacturer’s shop drawings shall include the,
Product data and samples (6” long x 24” width) on all building skin and roof systems,
window systems, and doors shall be approved by the owner prior to ordering. A copy of
the product data and samples, as required, to be submitted to the owner.
Product data and samples (6” long x 24” width), on all color and material samples of all
finished surfaces including the interior and exterior materials shall be approved by the
owner prior to ordering. A copy of the product data and samples, as required, shall be
submitted to the owner.
7. Submittal of the calculation’s booklets and shop drawings, from the manufacturer of the pre-
fabricated buildings, to the pre-listed structural engineer for the design of the foundation, slab
and foundation wing wall/s. Owner’s approval is required prior to submission to engineer. A
copy of all calculations, plans, and shop drawings shall be submitted to the owner.
8. Structural foundation drawings and calculations shall include the foundation design based on
the reactions submitted by the manufacturer, slab and reinforcement design, anchor bolt, base
plates, the lift slab, and the foundation wing wall/s design along with all pertinent details, and
Page 2/13
Edit Online
Free Download

Detailed Construction Scope of Work Template PDF

Favor this template? Just fancy it by voting!
  •  
  •  
  •  
  •  
  •  
(1 Votes)
5.0
Related Forms
  •  
  •  
  •  
  •  
  •  
2 Page(s) | 3591 Views | 117 Downloads
  •  
  •  
  •  
  •  
  •  
1 Page(s) | 2356 Views | 159 Downloads
  •  
  •  
  •  
  •  
  •  
4 Page(s) | 4891 Views | 104 Downloads
  •  
  •  
  •  
  •  
  •  
1 Page(s) | 14153 Views | 2664 Downloads
  •  
  •  
  •  
  •  
  •  
2 Page(s) | 4157 Views | 296 Downloads