Business Impact Analysis and Recovery Strategies Recommendations Report

EXECUTIVE SUMMARY
Page 12
Revised BIA Priorities and Recovery Time Frames
# of Applications
Priority Recovery Time Frame
Server Desktop
%
Critical 1 day or less 12 1 37%
Essential 2 days 2 6%
Important 5 or more days 12 8 57%
Total # Applications 35 100%
Based on the input from the departments, the most critical RGRTA server applications were
identified and are listed in the table below. The first column shows the original priority / recovery
time frame identified for the application during the BIA process. The second column shows the
revised priority / recovery time frame for each application which was determined during follow-up
meetings.
Application Original Priority Revised Priority
1. ACS (all modules) Critical Critical
2. Highline Critical Critical
3. Trapeze Suite Critical Critical
4. Fleet Maintenance (AS/400) Critical Essential
5. Logic Tree Critical Essential
6. Ramco Financial Suite Critical Essential
7. Symposium Critical Essential
8. APCs Critical Important
9. Charter Critical Important
10. Luminator / Twin Vision Critical Important
11. Petro-Vend Critical Important
12. Pictometry Critical Important
The most critical RGRTA server applications have been identified as:
ACS (all modules)
Highline
Trapeze Suite
Page 15/196
Free Download

Business Impact Analysis and Recovery Strategies Recommendations Report PDF

Favor this template? Just fancy it by voting!
  •  
  •  
  •  
  •  
  •  
(3 Votes)
4.7
Related Forms
  •  
  •  
  •  
  •  
  •  
4 Page(s) | 2751 Views | 65 Downloads
  •  
  •  
  •  
  •  
  •  
14 Page(s) | 3396 Views | 6 Downloads
  •  
  •  
  •  
  •  
  •  
2 Page(s) | 771 Views | 3 Downloads
  •  
  •  
  •  
  •  
  •  
2 Page(s) | 990 Views | 6 Downloads
  •  
  •  
  •  
  •  
  •  
2 Page(s) | 895 Views | 7 Downloads